Production Report: Pivot Power
by jordanIt’s time for a production report on Pivot Power, our highly-anticipated flexible, adjustable electrical power strip. Power up; this is a long one.
What we’ve been up to:
We raced to get all the electrical and mechanical engineering done in order to begin the UL approval process, and on September 9 we sent off the functioning prototypes that we built along with all of the necessary electrical specifications.
Through our contact at UL, we were promised an expedited preliminary investigation (preliminary investigation happens before you start tooling in a factory, full investigation comes once you have an off the tool product). However, we soon learned that UL was unable to hit their expected finish date of September 15. Here’s what they told us:
We need to address the construction of the RPT with additional staff members throughout our various offices and come to a consensus on the requirements. Since this type of construction is not directly addressed by the standard (UL1363) we need to consider additional requirements for evaluation and testing. Due to this, we will not be able to complete this preliminary investigation project until we have discussed further internally.
Essentially: Pivot Power is so innovative that UL has never seen anything like it. When it came across their plate, it blew their minds, and now they need to get more opinions, discuss further, and continue to have their minds blown.
Note in the image of the fully assembled: There are actually six outlets on Pivot Power even though the proto only has five. Also, we’ve added an extra segment for the on/off switch and the circuit board to be housed in.
While it’s nice that our products have this effect, we’re admittedly getting crushed on our hopeful timeline. To help combat that, we’ve spoken with our contact at UL and we’ve gotten a little more insight into the finer details of what is holding them up. It mostly has to do with the combination of wiring and metal contacts and how they are connected. Our engineers have been extremely quick to respond and make the necessary revisions based on this initial feedback.
What we expect going forward:
On September 27, UL pushed back their preliminary timeline again. We’ll continue to wait on UL’s preliminary approval, which they estimate should arrive on or before October 13, and make revisions if necessary as soon as we hear anything. Since pushing the deadline back twice has brought us from an expedited timeline to a normal timeline, we think it is reasonable to believe they will come through and deliver by the 13th.
Meanwhile, our partners in China will continue to work with our factory to figure out a way of keeping costs down. Since the design is so innovative and complicated, assembly fees are quite high right now. Next week, after they return from their National Day holidays, our engineers in China will begin working to simplify the internal structure so the assembly is easier and therefore less costly.
If all goes according to plan, we’ll get the UL preliminary approval by October 13, and in the next two or three weeks will have cut costs in assembly fees and will be able to begin tooling.




4 Comments
By Daniel Schier
What a challenge that must have been. Pretty cool to see it’s innards.
By Tyrel Hatfield
Good Job, Jordan! Ben, give that guy a raise!
By grangermdk
Very cool, thanks for the update
By urbenz
So neat to see how hard it is to release a product. I’m glad their minds are getting blown away. Hopefully they’ll tell their friends.